Blog Article
SDC Austin Progress Q3 2023
Construction for SDC Austin is coming together, with the first building tracking for an on-time delivery in January!
Construction for SDC Austin is coming together, with the first building tracking for an on-time delivery in January!
We’re excited to share that the construction of Sabey Data Centers’ newest data center in Austin, TX is tracking for an on-time delivery in January, 2024. We’ll be offering early occupancy starting in November of 2023.
Our construction team has been working around the clock, making amazing progress. Some of our recent milestones include:
• All the exterior walls are now up!
• Pad site has been developed and is now ready for the new 160MW substation.
• Chillers are installed and ready for service.
• Diverse fiber entry points are in place.
Stay tuned for announcements and updates in Q4 as we put the finishing touches on the first of two planned buildings.